Project Title |
Client |
Industry |
Date |
Duration |
Project Summary |
Safety Case Scoping Study for the Jubilee Line Extension |
London
Underground Limited |
Transport
(Rail) |
1993 |
3
months |
PM
Safety Consultants Limited was responsible for scoping out the complete
requirements for a railway Safety Case. The scoping study included both the
technical requirements and the strategic options available to the management
team to complete the safety case and maintain "ownership", a key HSE
requirement. In addition to the production of the safety case itself, PM
Safety Consultants Limited personnel also gave advice on aspects of living
PRA, and the concept of a rolling programme for the safety case.
Presentations on these topics were given to senior management and at project
director level, so that the London Underground Jubilee Line extension team
could formulate their safety strategy. The advice PM Safety Consultants
Limited gave was to build up an in-house team with a significant amount of
work done within London Underground Limited. In addition, the use of
consultants for some specialist areas was recommended. |
Hazards Review / QRA Model & Database for the Jubilee Line
Extension |
London
Underground Limited |
Transport
(Rail) |
1993 |
4
months |
Working
directly for London Underground Limited, a major railway operator, PM Safety
Consultants Limited personnel assisted in the production of the detailed
technical specification for the Hazards Review package to support the
eventual production of the Safety Case for the proposed new railway line. The
production of the specification required a knowledge of the existing studies
performed, together with an understanding of the methodology to be employed.
The intention was to use the technical scope of work in a competitive tender.
This project was undertaken in one month.
PM Safety Consultants Limited were also involved in setting up the initial
Quantified Risk Assessment model for a major railway undertaking, and
producing a database of fault data. The database was set up on Alpha IV using
fault data for the existing and operational section of the railway, as well
as other relevant fault models. The database provided the information
necessary for the Fault Tree Analyses (FTA) using TGR software. Consequence
analyses were performed by means of Event Tree Analyses using ETA software. A
comparison was made between these findings and the results obtained from an
earlier risk model for the existing line, and any weaknesses were highlighted.
The new risk model and database formed the basis for the proposed hazards
review, where both sections of line would become interfaced. |
Railway Safety Case |
Union
Railways Limited |
Transport
(Rail) |
1993 |
3
months |
Working
directly for Union Railways Limited (a division of British Rail), PM Safety
Consultants Limited assisted in the development of the bid evaluation
procedures for the railway safety case and peer review contracts. In addition
to the preparation of the evaluation procedures, PMSC personnel provided an
interim peer review function pending the appointment of the peer review
safety consultant. Topics covered as part of the interim peer review were as
follows:
- Initiating
fault schedules
- Safety case content and
format
- Probabilistic
criteria
- Single
versus dual track tunnels
- Fault schedule hazard
log
- Corporate evacuation
policy and strategy.
Post Project Note
Union Railways Limited became the client company for the Channel Tunnel Rail
Link, responsible for the day-to-day development of the project under the
direction of Rail Link Engineering Limited. |
Safety Analysis Report |
Railtrack
Major Projects Division |
Transport
(Rail) |
1994 |
9
months |
Working
directly for Railtrack Major Projects Division South Zone, PM Safety
Consultants Limited was responsible for co-ordinating the production of the
Safety Analysis Report on clearances for the passage of both the new
passenger-carrying rolling stock (Class 373/1 - Eurostar) and freight
vehicles over the existing infrastructure between the Channel Tunnel and
London. The study included the management of a civil engineering
sub-contractor (CEDAC, Croydon) providing support to the analysis. PMSC
personnel prepared scopes of work for the sub-contractor and then managed the
programme of work throughout the project. The analysis was undertaken using
the latest calculations for the derived Kinematic Envelope for the Class 373
train vehicles, and covered all major structures adjacent to the railway
routes, i.e. tunnels, station platforms, under-bridges, over-bridges,
footbridges and other miscellaneous structures such as viaducts and gas
pipes. In total some 700 structures were reviewed, covering Channel Tunnel
routes 1, 2, 3 and 4. |
Hazards Operability Study for Ballast Gluing - Channel Tunnel
Routes |
Railtrack
Major Projects Division |
Transport
(Rail) |
1994 |
3
weeks |
Working
directly for Railtrack Major Projects Division South Zone, PM Safety
Consultants Limited was responsible for organising a HAZOP study on the topic
of ballast gluing for the provision of lateral restraint. Ballast gluing was
used extensively on the South Zone Channel Tunnel routes, and as such a HAZOP
was organised and implemented to identify any major hazards posed by the
process. The role of PMSC personnel was initially to prepare the HAZOP brief
and send it to the attendees for comment and review, and then to perform the
role of HAZOP secretary at the meeting itself, and prepare the minutes of the
meeting together with the detailed HAZOP action sheets. Finally, once all the
HAZOP action sheets were closed out, a full report on the HAZOP was prepared
for submission to the appropriate SAP in support of the overall safety case
for clearances. |
Risk Analysis of LTF 25 Wheel Set |
Blue
Print Engineering Services for Powell Duffryn |
Transport
(Rail) |
1995 |
6
months |
PM
Safety Consultants Limited was responsible for providing advice on how to
conduct a risk analysis on the Low Track Force (LTF) 25 on behalf of Powell
Duffryn, the bogie wheel set designers. The owner of the wheel sets was ARC
operated via Mendip Rail, mounted on hopper vehicles used to carry aggregate.
The approach was to hold a HAZOP session using keywords and deviation agreed
prior to the HAZOP in the briefing note which was sent to all participants.
The HAZOP identified several guidewords which represented major component
items in the wheel set, including:
- Wheel seat
- Bearing seat Axle
- Bearing inner ring, cage and outer ring
- Axlebox
- Wheel set re-assembly
- External factors
- Management of the fleet
At each stage the deviations were applied to the guidewords, the potential
hazards discussed and any protection available to mitigate the hazard
identified. Each scenario was then ranked via the risk matrix in terms of
overall risk. The process was fully documented in a report which was
submitted to the vehicle acceptance body The Engineering Link. |
QRA of LTF 25 Wheel Set |
Blue
Print Engineering Services for Powell Duffryn |
Transport
(Rail) |
1995 |
3
months |
PM
Safety Consultants Limited was asked to provide a Quantified Risk Assessment
(QRA) for the LTF 25 wheel set. The vehicle acceptance body, The Engineering
Link, mandated that the QRA would be required in order to facilitate
consideration of allowing the LTF 25 wheel set back into service. The QRA was
conducted based on the hazardous sequences identified by the earlier HAZOP.
The QRA also included a human reliability assessment using the Human Error
And Reduction Technique (HEART) applied to the wheel set inspection regime.
The QRA was documented, and after comments was accepted by the Vehicle
Acceptance Authority. The wheel sets were allowed back into service. |
Heathrow Express EMU Document Review |
Interfleet
Technology, Derby UK |
Transport
(Rail) |
1995 |
2
months |
PM
Safety Consultants Limited was requested to act in the role of an independent
assessor and carry out a review of the Reliability, Safety and
Maintainability Plan, and also a Failure Mode, Effect and Criticality
Analysis documents prepared by Siemens, relating to the new trains for the
Heathrow Express. This review was
conducted on behalf of Interfleet Technology, Derby who were acting as the
procurement agent for the British Airports Authority. |
Failure Modes, Effects & Criticality Analysis of Signalling -
Jubilee Line Extension |
Westinghouse
Signals Limited |
Transport
(Rail) |
1996 |
3
months |
Working
for Westinghouse Signals, PM Safety Consultants Limited were responsible for
the preparation of the Failure Modes, Effects and Criticality Analysis
(FMECA) for the Speed and Location Module, which was part of the moving block
signalling system to be installed on the London Underground Limited Jubilee
Line extension. This work required a detailed understanding of digital
electronics and the system operation. The FMECA was undertaken at pin level,
i.e. stuck HIGH and stuck LOW. Wherever possible, the built-in test equipment
BITE was identified as a means to reveal faults. The FMECA was conducted over
three months, and involved extensive consultations with the designers of the
module.
Post Project Note
In 1998 a decision was taken not to
implement a moving block signalling system, and a fixed block system was
installed instead. |
Clearance |
Allot
& Lomax |
Rail |
1995 |
6
Months |
Working
as an advisor to Allot & Lomax, PM Safety Consultants worked on the
safety aspects of the EPS / Networker Project on the ECML. |
Various small safety and reliability projects for Interfleet Ltd |
Interfleet |
Transport
(Rail) |
Jul-95 |
3
Months |
1)Production
of task safety plans and associated guidance for the Interfleet engineers
that includes:
Risk Assessment
Hazard Sheets
Risk Assignment
Risk Identification
Risk Management
2)Reliability
Apportionment exercise for the class 91 drive link vibration detection system
(18 man hours)
3)HST Halon Replacement Project |
Hazards Operability Study Guidance Documents |
Railtrack
Major Projects Division, North West Zone |
Transport
(Rail) |
1995 |
2
weeks |
Working
directly for Railtrack Major Projects Division North West Zone, PM Safety
Consultants Limited was responsible for the production of a HAZOP guidance
report. The guidance report presented the basis of the technique, and the
application of keywords and deviations to the processes being considered by
the HAZOP. In addition, the document included guidance on how to organise and
report the HAZOP by the production of briefing notes prior to the meeting,
minutes and actions after the meeting, and the final HAZOP report once the
actions were closed out. Schematics were also used to facilitate
understanding of the process by non-safety specialists. |
European Passenger Services Operations North of London |
Railtrack
Major Projects Division, North West Zone |
Transport
(Rail) |
1996 |
6
months |
PM
Safety Consultants Limited personnel acted in the Planning Supervisor role
for the EPS North of London project. In addition, under the CDM regulations,
PMSC personnel developed the required project Safety Cases for each of the
routes being used by EPS rolling stock (Class 373/2) in the North West. The
route considered were as follows:
- The primary route into
Manchester Piccadilly via the Styal line.
- The core route into Manchester Piccadilly via Stockport Station.
- The diversionary route via
Macclesfield.
- The route north
of Manchester to the West Coast Main Line.
- Parts of the West Coast
Main Line.
In addition to the safety case work, PM Safety Consultants Limited personnel
were involved in the hazards identification studies for the Overhead Line
Equipment, Signalling and P/Way works. The work itself was mainly a
conversion from a dual track circuited system with impedance boxes to a
return conductor system using one rail for traction current and one rail for
the signalling track circuits. This approach was aimed at reducing the
instance of wrong side failures and other telecoms interference. Other
specific hazards reviews were organised and reported for the proposed station
works at Piccadilly Station, and the reconstruction of a bridge in the
Sandbach area (Bridge 14). |
Southern Track Renewals |
STRC |
Rail |
Jan-96 |
2
Months |
General
Safety Advice on Railway Maintenance infrastructure projects |
Simplified Approach to the Development of Railtrack MPD Project
Safety Cases |
Railtrack
MPD East Anglia |
Transport
(Rail) |
1996 |
2
months |
Working
directly for Railtrack MPD East Anglia, PM Safety Consultants Limited
prepared a report on a simplified approach to the development of a project
Safety Case and the supporting risk assessment process. An insight into the
work was gained whilst working on the EPS beyond London infrastructure change
project Safety Case and Risk Assessment. The approach of simplifying the
process for small repeatable infrastructure change projects was aimed at
reducing costs and standardising the approach to risk assessment by a
consideration of generic risks wherever possible. During the development of
the report, extensive discussions were held with Railtrack MPD East Anglia
safety personnel in order to agree the eventual simplified process. |
Risk Assessment for the Stafford Cross-Over |
Owen
Williams Railways for Railtrack Midlands Zone |
Transport
(Rail) |
1997 |
1
month |
Working
as a sub-contractor to Owen Williams Railways, PM Safety Consultants Limited
organised and conducted a project risk assessment for the proposed
implementation of the Stafford Cross-Over. This work involved the procurement
of software to provide the planning tools, and the use of the Monte Carlo
simulation. The first step was the development of a detailed plan for each of
the proposed five possessions. The plan was then subjected to a detailed
review to investigate the possible impacts of over-runs on each of the
individual tasks. This information was then put into the Monte Carlo
simulation software, and a profile for the likelihood of successfully
completing each possession was produced. The output from the analysis was fed
back into the strategy for the possession planning in order to have a high
confidence that the work to be undertaken could actually be completed within
the planned possessions, ie. to minimise the risk of possession over-run and
thus avoid penalty costs which are inevitably incurred when possessions
over-run. |
Safety Case for ECML Infrastructure Change to Enable Class 373/2
& Class 365/5 |
Railtrack
Major Projects Division London North East & East Anglia |
Transport
(Rail) |
1996/1997 |
8
months |
PM
Safety Consultants Limited prepared the first draft and subsequent updates of
the project safety case for the infrastructure change to enable the running
of Class 373/2 Regional Eurostar and Class 365/5 Networker on the East Coast
Main Line and the route up to King's Lynn. The scope of the infrastructure
change was varied and covered the following works:
- Permanent Way /
Civils
- Re-siting of
minor lineside features
- OHLE works, including
re-registration
- Telecommunication
works
- Signalling
works
PM Safety Consultants Limited also facilitated the risk assessment process
with the various design teams on the project. A risk assessment report was
prepared, and a hazards log or register was developed. The methods adopted
for this study were those specified in the Railtrack MPD Divisional Manual,
Volume 10. A key aspect of this part of the work was to demonstrate by a
systematic approach that risks had been controlled to as low as reasonably
practicable (ALARP). The safety case and the supporting risk assessment
report were submitted to the Railtrack zonal Safety Review Groups, and
comments addressed accordingly. Both documents were accepted by the London
North East and East Anglia zonal Safety Review Groups. PM Safety Consultants
Limited personnel also complied the CDM Health & Safety file, acting on
behalf of MPD as the Planning Supervisor. |
Secondment of PMSC Personnel Safety Support to Heathrow Express
Project Team |
Siemens
Transportation, Germany |
Transport
(Rail) |
1997 |
12
months |
PM
Safety Consultants Limited seconded two personnel to Siemens Transportation
in Erlangen, Germany, to assist with the Safety Assurance for the Heathrow
Express project. The work involved various safety analysis tasks on a variety
of train systems. |
Secondment of a Safety Engineer to WCML RM - Safety Manager,
Re-Signalling |
Railtrack
WCML Route Modernisation |
Transport
(Rail) |
1996 |
12
months |
Working
directly for Railtrack WCML Route Modernisation, PM Safety Consultants
Limited seconded a specialist safety consultant to act as Safety Manager,
Re-Signalling. The remit was to co-ordinate the approach to risk management
on the re-signalling aspects of the route modernisation, which included Train
Control Systems. |
Secondment of a Safety Engineer to WCML RM - Safety Risk Manager |
Railtrack
WCML Route Modernisation |
Transport
(Rail) |
1996 |
12
months |
Working
directly for Railtrack WCML Route Modernisation, PM Safety Consultants
Limited seconded a specialist safety consultant to act as Safety Risk
Manager. The remit was to co-ordinate the approach to risk management across
the project as a whole, and to manage the production and use of the safety
risk register or hazards log. The position was based at Stanier House in
Birmingham, and the engineer reported to both the Director of Safety and the
Project Director. |
Secondment of PMSC Personnel - RAM Co-ordinator |
Railtrack
Thameslink 2000 |
Transport
(Rail) |
1998/1999 |
4
months |
PMSC
Limited placed an engineer on attachment at Railtrack Thameslink offices.
Initially the remit was to provide RAM advice within the project team, and to
write the scope of work for the RAM modelling for the infrastructure
improvement plan. The contractor eventually selected was Jardine, using their
TRAIL model. |
Secondment of PMSC Personnel - Regional NE Railways / Northern
Spirit Project |
Siemens
Transportation, Erlangen, Germany |
Transport
(Rail) |
1999/2000 |
20
months |
Support
on Northern Spirit EMU train unit and other projects as required:
- Review/rework FMECAs & Fault Trees
for Class 333.
- Review and rework of base event data.
- General support in the safety and
reliability analysis process for NS.
- Support production of EMU train unit
technical description.
- Review of
Train Structure Tree (EMU system breakdown).
- Production of Reliability and Safety
Programme Plans.
- Preparation of Reliability Critical Items
List and Technical Causalty Criteria documentation.
- Review targets & results from the
Safety Targets Application Process.
- General support in the safety and
reliability analysis process for NS project.
- Production of Hazard Tree / Accident
Group Tree.
- Organisation of Hazard Identification
Meetings and Minutes.
- Definition and general support of the Hazard Identification, Management &
Close-out process.
- Production of the complete project Hazard Matrix and
Hazard Log.
- Production and support of Safety Case
documentation.
- Preparation and support of Safety Case
Submissions to independent assessor/auditor/Railtrack.
- Support response to independent
assessor/Railtrack comments.
|
Systems Assurance for C751B EMU |
Kawasaki
Heavy Industries, Nippon Sharyo Joint Venture |
Transport
(Rail) |
1998/1999 |
15
months |
PM
Safety Consultants Limited was appointed by the KNS Joint Venture to
undertake the Systems Assurance activities for a new-build 6 car EMU for the
Singapore MRT. The scope of this project included the following
activities:
- Development of the Safety Assurance Program Plan.
- Development of RAM
Assurance Program Plans.
- Detailed PHA and
HAZOP studies for each train system.
- Quantified Risk
Assessment.
- Safety Critical Items
List.
- FMECAs.
- Reliability and
Maintainability predictions.
- Safety Assurance Summary
Report.
- RAM Demonstration Test Plan & Procedure
All the activities were documented and submitted to the Singapore Land
Transit Authority for their acceptance. |
Support to the KIT Consortium for C830 Marina Line Bid |
Kawasaki
Itochu Toshiba Consortium |
Transport
(Rail) |
1999/2000 |
9
months |
The
KIT Consortium appointed PM Safety Consultants Limited as the member
responsible for Systems Assurance for the C830 Marina Line project bid (a new
underground railway system in Singapore). PM Safety Consultants Limited
provided the following input to the bid documentation:
- Initial Systems Assurance
Program Plans
- Detailed review of the
Singapore land Transport Authority (LTA) Systems Assurance requirements and
targets
- Development of an overview
system-wide Preliminary Hazards Analysis
- Development of an overview
Operational Philosophy and Preliminary Fault Analysis for a driver-less,
fully automated railway.
|
Systems Assurance for C751B EMU - R & M |
Kawasaki
Heavy Industries, Nippon Sharyo Joint Venture |
Transport
(Rail) |
1998/1999 |
15
months |
The
scope of the PMSC remit for C751B was extended to include all reliability and
maintainability activities in addition to safety related activities. |
Secondment of PMSC Personnel - Safety Audit for New Light Railway,
Kuala Lumpur |
Bombardier
Transportation Systems Limited (Kuala Lumpur) |
Transport
(Rail) |
1999 |
3
months |
PM
Safety Consultants Limited attached a safety engineer to Bombardier to
provide operational safety support services and assist the Commissioning
Manager in certifying the safety of a new light railway system in Kuala
Lumpur. The role was to provide a safety audit function on site to ensure
that all the appropriate safety measures were installed correctly and fully
integrated into the operational railway. |
Clearances Risk Assessment, West Coast Main Line Rugby - Brinklow
Section |
Scott
Wilson Railways Limited for Railtrack |
Transport
(Rail) |
1999 |
1
month |
PM
Safety Consultants Limited was sub-contracted by Scott Wilson Railways to prepare a clearances risk assessment
for the Rugby to Brinklow section of the West Coast Main Line. The assessment
reviewed the clearances at each major structure adjacent to the route,
including the following:
- Under - bridges
- Over - bridges
- Foot bridges
- Viaducts
The risk assessment was conducted using the guidance provided in the
Railtrack Yellow Book. The final Clearances Risk Assessment report was
accepted by Railtrack. |
Secondment of PMSC Personnel |
Bombardier
Transportation Systems Limited (Canada) |
Transport
(Rail) |
2000 |
3
months |
PMSC
Limited seconded a safety engineer to the Safety department of Bombardier
Transportation Systems Limited in Kingston, Ontario. During this attachment
period the consultant was involved with several rail projects currently being
managed by Bombardier, principally the Vancouver Sky Train. This contract was
part of the periodic support provided by PMSC to Bombardier. |
SP 1900 |
Itochu,
Kinki Sharyo, Kawasaki (IKK) Consortium |
Transport
(Rail) |
2000 |
1
year |
PMSC
Limited assisted IKK in the preparation of key safety submissions for the SP
1900 EMUs for East Rail and West Rail. The remit was an initial review of the
miscellaneous electrical systems using the HAZOP technique, followed by a
detailed QRA for each route (using KCRC-approved methodology). The
culmination of the work was the production of the Design Stage Operational
Safety Reports (OSRs) for East Rail and West Rail SP 1900 rolling stock. |
Taiwan High Speed Rail Project |
Taiwan
Shinkansen Corporation (TSC) |
Transport
(Rail) |
Dec-00 |
6
years |
PMSC
Limited has been appointed as the RAMS advisors for the consortium providing
the core systems for the new high speed railway project between Taipei and
Kaohsiung throughout the preliminary design phase. Further details are confidential. |
Hazard Review for Train Catering System |
INBIS
Technology, Derby, UK |
Transport
(Rail) |
2001 |
2
months |
INBIS
are the supplier of the Kitchen and Galley for an Alstom train being supplied
to Great Western in the UK.
PM Safety
Consultants were requested to assist with the formal closure of 130 hazards
identified as a result of the Kitchen and Galley.
The activities conducted were as follows:-
- Initial review of
documentation
- Visit
to Train at the Washwood Heath site
- Meeting with Alstom to
discuss the strategy to be taken
- Hazards Review meeting to
review the hazards
- Preparation of the Hazards
Log
- Identification of all
preventative and/or mitigation measures provided by the design
- Closure of each of the 130 Alstom Safety Feature Action Sheets
- Preparation of report to
document the process.
The work was formally submitted to Alstom in the
form of a master file containing the report, SFAS sheets and Hazards Log. |
Secondment of PMSC Personnel |
Siemens
Transportation, Erlangen, Germany |
Transport
(Rail) |
2001 |
12
months |
Safety
Case and Vehicle Acceptance Body (VAB) support work related to the Desiro UK
project.
The Desiro UK train is the third EMU design provided to the UK railway
market by Siemens (and its partners). Desiro UK follows Heathrow Express and
Northern Spirit. Initially Desiro UK is being provided to Angel Train Leasing
and has not been leased by them to operating companies.
VAB work involves the management and support of design activities directly
related to satisfying the Railway Group Standards mandatory requirements. The
work is specifically related to train electrical and control systems as well
as vehicle testing requirements.
The safety work involves activities such as hazard identification, FMECA
preparation and Fault Tree Modelling. These are all undertaken as part of the
Desiro UK Safety Case process. |
Secondment of PMSC Personnel |
Siemen's,
Krefeld, Germany |
Transport
(Rail) |
2001 |
12
months |
The
remit was to provide general safety support to the non-EC&S issues for
the new DESIRO train. |
8303 Singapore Project |
Singapore
LTA |
Rail |
2001 |
<
1 month |
Bid
proposal to send 2 engineers to Singapore. Project not awarded (PMSC 2nd out
of 6 bidders) |
Secondment of PMSC Personnel |
Railcare
limited, Coventry |
Rail |
2001 |
3
Weeks |
PMSC
worked directly with Railcare collecting Data for an FMECA report. |
Systems Assurance Presentation |
Singapore
LTA |
Rail |
2002 |
3
Day Course |
PMSC
developed a tailor made Systems Assurance course for the Singapore Land
Transport Authority. The aims of this course were as follows:
- Clearly describe the managerial and project issues associated with Systems
Assurance
- Extol the virtues and the benefits of Systems Assurance to
the engineering fraternity
- Provide a grounding for the non-expert in Systems Assurance principles and
methods using slides and worked examples
- Provides an overall programme and framework for Systems
Assurance and some insights of why things go wrong or how to get it right
first time.
- Modules of the course covered Safety Management Principles; Safety
Management Standards; Safety Management Concepts; LTA Safety Management
Process and Related Topics; Overview of Systems Assurance Techniques.
- The Safety Management Principles Module covered:
- Basic Principles Of A Risk Based Safety
- Management Programme
- Origins Of Systems Assurance
- Discussion And Review Of Best
Practice
- Systems Safety Assurance (Outline Concepts)
- Safety Policies
- Risk Management And Risk Management Criteria
- The Concept Of ALARP (Legal Origin)The Safety Management Standards Module
Covered:
- Applicable Safety Management Standards
- Walk Through EN 50126
- Walk Through HSE 2000
- Walk Through EN 50129 And IEC 61508
- What The Standards Don't Say i.e. "Best Practice"
- Life Cycle Programme Issues
- Worked Example (Application Of
Standards)The Safety Management Concepts module covered:
- Safety Risk Management
- Safety Integrity
- Development Of Safety Requirements
- Allocation Of Requirements
- SIL Determination
- System Realisation
- Safety Validation
- Brief Review Of Other Standards And Approaches
- The LTA Safety Management Process and Related Topics module covered:
- Safety Programme Planning
- Requirements And Specification Management
- Verification And Validation
- Typical Project Flow Chart
- The Overview of Systems Assurance Techniques module covered:
- Safety Criteria Checklists
- FMECA
- HAZOP Methods
- Hazards Analysis (Including PHA)
- Quantified Risk Assessment (QRA)
Modules also included a variety of worked examples to exemplify the points
made in the body presentation.
|
Secondment of PMSC Personnel |
Siemens |
Rail |
2002 |
12
Months |
This
project involved PMSC working directly with Siemens Krefeld on the Desiro UK
project. Work involved attendance of Hazard Close Out meetings; FMEA for
Meeting Train Communication and review of draft FMEA report; Review of Hazard
Close Out documents; Review of Brake Communication Network including
Multifunctional Vehicle Bus revised FMEA report; Review of Door FMEA reports;
Review of Door Fault Trees Report; Preparation work for and involvement in
HAZID studies. |
Secondment of PMSC Personnel |
Thames
Link 2000 |
Rail |
22-Apr-02 |
12
Months |
Working
directly for Railtrack Thameslink 2000 project PMSC provided technical
support by assisting Railtrack in the preparation of the Thameslink 2000
Engineering Safety case, which addresses all 33 of the major scopes of the £1
billion project. The required safety studies associated with the
infrastructure changes being identified and will form the safety deliverables
for the contractors. in addition the interface between Railtrack and the
submissions to the internal and external approval bodies is being managed. |